Change the burndown to remaining estimate and time spent in Days

Shirley Jhirad October 29, 2017

Hi,

Today, doing so will show the burndown in hours. Is there any way to make it burndown in days?

 

1 answer

0 votes
Gregor Kasmann_Actonic
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 29, 2017

Which version of JIRA do you use? Cloud or On-premise?

Shirley Jhirad October 31, 2017

On prem

Suggest an answer