Change first week of year

Jean-Michel Griveau May 24, 2016

Hello

We are using TimeReports and we have found an offset in week number.

Today, 25 may, is a day of week #21. If we are displaying the time report in monthly view, all logged work appears in week #22. In 2016, week #1 started 4 january.

Does a parameter of offset the first day of year exists ?

Best regards

Jean-Michel

2 answers

1 vote
Damien Braz
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 24, 2016

Hi Jean-Michel,

 

You can try this solution: https://confluence.atlassian.com/jirakb/change-week-number-in-jira-s-calendar-802171323.html

 

Best regards, Damien.

0 votes
Jean-Michel Griveau May 25, 2016

Unfortunately, it does help us, we are on JIRA Cloud and this solution can not be applied.

However, I do the modification, the only visible effect is monday à first day of week, but week number still wrong.

 