Carried over incomplete tasks to the next sprint

When you come a sprint, all open stories get carried over to the next sprint. How should I handle the modification of the task "Original Estimate" and "Remaining Estimate"? For example, from the previous sprint, the "Original Estimate" was 10 hours and the "Remaining Estimate" was 4. If the task gets carried over to the next sprint, should you update the "Original Estimate" to be reflective of the remaining hours left on the task? 

Thank you,

Kai

1 answer

Depending on the team leads, we either

1) Reset the original estimate but it may not be equal to the remaining estimate since the cost might be greater to continue to work.

2) Clone the issue so you can close off the original issue and start using the cloned copy.

In any case we want the work estimate never to be greater than what was estimated for the sprint.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

69 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you