Carried over incomplete tasks to the next sprint

When you come a sprint, all open stories get carried over to the next sprint. How should I handle the modification of the task "Original Estimate" and "Remaining Estimate"? For example, from the previous sprint, the "Original Estimate" was 10 hours and the "Remaining Estimate" was 4. If the task gets carried over to the next sprint, should you update the "Original Estimate" to be reflective of the remaining hours left on the task? 

Thank you,

Kai

1 answer

This widget could not be displayed.

Depending on the team leads, we either

1) Reset the original estimate but it may not be equal to the remaining estimate since the cost might be greater to continue to work.

2) Clone the issue so you can close off the original issue and start using the cloned copy.

In any case we want the work estimate never to be greater than what was estimated for the sprint.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

100 views 1 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you