I'm trying to diagnose why a Sprint cannot be completed - The complete Sprint Option is not available. I've checked these issues for the user and the issues and all clear:
I DID notice that all the issues in the given sprint that cannot be completed have a Closed status. The resolution is Done, but the issue is closed.
Is this what's causing the "complete sprint" option to not be available? Can I do anything about it?
Update: JQL showed one issue that is supposedly in this project (Although - it's in a completely different project, HOWEVER, the board that issue appears on is a different board, I checked the sprint IDs and they vary. There's no link between this one issue and the sprint that cannot be closed.
There are sprints that share names.
Depending on the version you are on, you might need Manage Sprints permission in the projects. Status shouldn't stop you from completing sprints.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.