Cannot choose the security level on creating a subtask

Rumceisz June 5, 2012

Hi All,

we cannot set the security level on a Sub task create screen.

I checked the screen schemes and the field configuration schemes: both contain the Security level field. What else must be checked??

Or is it connection with the parent issue?

Can you please help?

Thanks in advance!

Rumi

3 answers

1 accepted

1 vote
Answer accepted
Norman Abramovitz
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 5, 2012

The security level is inherited from the parent and the security level cannot be changed on a sub-task.

Please see the note in the documentation that states this.

https://confluence.atlassian.com/display/JIRA050/Creating+a+Sub-Task#CreatingaSub-Task-Creatingasub-task

Rumceisz June 5, 2012

Hi Norman.

Thank you!

0 votes
Laurent Di Pasquale August 7, 2012

Hi Norman,

Can this inheritance be cancelled? It would be so useful to generate hidden subtasks from a customer issue in order to do the internal job.

0 votes
Laurent Di Pasquale August 7, 2012

Is there any other way? Linking issue takes more time...