Can you report on tickets that have been moved between projects?

Adam Garner September 14, 2014

In our current JIRA instance we have a project that is used as a master backlog. Once a ticket/issue has been reviewed/triaged is is moved into the relevant project to be prioritised by the product owner for completion by the sprint team.

How can we report on the issues that have been moved from this master backlog project to others? 

To further that, 

How can we report on the performance of this issue, if the ticket was raised in this master project and then completed in another? 

2 answers

0 votes
Adam Garner September 14, 2014

Thanks @Jobin Kuruvilla

Looks like this plug in provide the JQL extension needed to get a report on the issues that have been moved. 

But can it provide a report to show how long it took to resolve, close this issue from being raised in one project to being completed in another? 

Thanks 

Adam

Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 14, 2014

It won't be able to tell you how it took to resolve unless you capture that in the scripted field or something. Bit of coding involved for that.

Adam Garner September 15, 2014

Thanks. Will need to look into this.

Calvin Chen April 8, 2015

Anybody find a way to track moved issues between specific projects?

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 14, 2014

You can use plugins like JQL Tricks plugin to find such issues. JIRA doesn't support it by default.

Suggest an answer

Log in or Sign up to answer