In our current JIRA instance we have a project that is used as a master backlog. Once a ticket/issue has been reviewed/triaged is is moved into the relevant project to be prioritised by the product owner for completion by the sprint team.
How can we report on the issues that have been moved from this master backlog project to others?
To further that,
How can we report on the performance of this issue, if the ticket was raised in this master project and then completed in another?
Thanks @Jobin Kuruvilla
Looks like this plug in provide the JQL extension needed to get a report on the issues that have been moved.
But can it provide a report to show how long it took to resolve, close this issue from being raised in one project to being completed in another?
Thanks
Adam
It won't be able to tell you how it took to resolve unless you capture that in the scripted field or something. Bit of coding involved for that.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Anybody find a way to track moved issues between specific projects?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use plugins like JQL Tricks plugin to find such issues. JIRA doesn't support it by default.