I've seen lots of data on using parallel sprints to run 2 sprints at the same time for separate business units or teams on a single project. I have not, however, seen any way to set up multiple consecutive sprints for the same project (future planning). Am I missing something very basic?
Thanks!
If you've already got a scrum board created, go to the backlog view (shows all sprints and backlog) and select the "Create Sprint" button at the top of the Backlog list.
Take a look here and see if this is what you are looking for. With this option turned on, it allows you to start multiple sprints in a single project.
https://confluence.atlassian.com/jirasoftwareserver/using-parallel-sprints-938845513.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
here is one specific to Jira cloud
https://support.atlassian.com/jira-software-cloud/docs/use-parallel-sprints/