Can you create alternative done statuses in company managed projects ?

James Deguara September 30, 2022

In all my workflows I have a final status called "Done". I gather that it is possible to have alternative statuses to done running at the same time e.g. Done, Won't Fix etc on TEAM MANAGED PROJECTS. Is this also possible in COMPANY MANAGED projects?

2 answers

2 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 30, 2022

Yes, you can have many "end" status in a company-managed project's workflow.

James Deguara October 2, 2022

Thanks for this Nic. I'll soon be trying this our on some test workflows.

1 vote
Answer accepted
Mohamed Benziane
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 30, 2022

Hi,

Welcome to the community.

Yes you can create multiple resolution for your Company managed project. Just, make sure to not be confuse between Status and Resolution, resolution is set when the issue reach its final status.

James Deguara October 2, 2022

Thanks for the answer @Mohamed Benziane

yes, I'm clear on the difference between resolution and status.