Can tasks be set to automatically have 0 time remaining after being moved from "in progress" into "done?"

Samuel Pehr October 30, 2014
 

1 answer

0 votes
Boris Georgiev _Appfire_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 30, 2014

You can add post-function "Update Issue Field" to the transition from in-progress to done and set the remaining estimate field to 0