Can't see progress on JIRA-Gantt

Jeff Dun April 8, 2014

Hi,

I don't see any progress bars on any of my tasks.

I've updated the colours to show progress as a nice purple.

The descriptions says:

Issue Type: Story Task Planned Start: 09/Apr/14 12:00 a
Assignee: XXX Planned End: 15/Apr/14 12:00 a
Original Estimate: 5 days Duration: n.a.
Time Spent: 0 days, 4 hours Baseline Start: 03/Apr/14 12:00 a
Estimated Time Remaining: 4 days, 4 hours Baseline End: 09/Apr/14 12:00 a
Progress: 10% Due Date: 09/Apr/14 12:00 a

Status: In Progress


The bar in the gantt doesn't show any purple.

Note also that the Duration says n.a. - any ideas why that is also? Some of our cases have duration, others dont'. This isn't related to progress - none of our tasks are showing progress.

Thanks

Jeff

1 answer

1 accepted

0 votes
Answer accepted
Frank Polscheit
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 8, 2014

Hi Jeff,

please use my JIRA to create a related support ticket: click on menu button with the question mark and select menu item "support request" in order to send an email with your problem and description including attached screenshots to illustrate that. Automatically, necessary information like JIRA version, Gantt-Chart version etc. are put into the email body for your convinience.

Kind regards,
Frank

Jeff Dun April 9, 2014

Thanks Frank, i've done so.