Can't make time tracking mandatory

Michael Benisti June 23, 2021

Hi

 

I would like to make time tracking mandatory.

In the workflow, when I add a rule "Verify a field value", in the picklist I pretty much have all fields except for the one I am looking for which is the time tracking standard jira field.

 

 

 

2 answers

0 votes
Rob Huijben October 6, 2021

I have tested this and the suggested settings described below work as expected @Michael Benisti. Does this solve your question?

0 votes
Tansu Akdeniz
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 23, 2021

Hi @Michael Benisti 

I guess you need to require "Original Estimate" in the workflow. Because Time tracking includes Original and Remaining Estimate fields.

Go to workflow -> related transition -> validators -> add validator -> fields required validator. You should make "Original Estimate" field required.

Best