If I try to set or edit a date in the gannt-chart edit mode, I always get the following error:

Error: Cannot update issue TM-1

Error parsing time: 2013-11-26T00:00:00-0600
gantt.edit.error

2 answers

1 accepted

1 vote
Accepted answer

Please download from my server at http://www.polscheit.de/plugins/jira/gantt-chart/gantt-3.0.1-JIRA6.jar and install it using JIRA’s upload add-on button on admin page „manage add-ons“. Does this work for you?

Regards,
Frank

Yep, that did it -- thanks!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,878 views 19 22
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you