Can i block a story from being added to a sprint if it DOES NOT have Story Points?

Mark Scandariato November 6, 2013

I don't want stories in my sprint if they have not been estimated. Is there a way to configure this?

7 answers

3 votes
Kim Poulsen
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 7, 2013

Personally I (as a Scrum Master) believe that people are over tools. Having the tools dictate what you should and should not do takes away social and personal responsibilities. Team members will start thinking that the tool will solve all problems and over time the team members will degenerate into tools slaves instead of highly motivated and responsible members.

I am from Scandinavia so I might be extremely biased towards individual freedom and responsibility and accountability over rules, razzia and tool enforced methods.

Reading through many of the questions and answers here it does seem that especially Asia (or people managing people from Asia) is struck by the "more rules"-concept.

So my answer is: More training. Agile Scrum is 200% about encouraging the team members to take personal stake in what they are doing rather than being treated as cattle being pushed arounf with yet another new stick called "Scrum in JiraAgile".

Encourage the team, talk about the values of Agile Scrum: Courage, Openness, Respect, Focus, Commitment

In regards to get the estimates right I suggest taking a good look at Commitment, Respect and Openness in regards to getting the sprints right.

Also do look into having a Definition of Ready and Definition of Done for the team as this will get the team to talk about exactly what the quality goals for all work is and the goal for good story preparation is.

I hope you can use this for something.

Deleted user April 22, 2021

nope... wrong answer

Like Roy Powell likes this
1 vote
Peter Van de Voorde
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 7, 2013

Hi Mark,

Why don't you make the field required on the Open -> In Progress transition?

They will still be able to add the stories to a sprint but they will not be able to start them untill a value is filled in for the Story Points?

But as Kim says : it's really a team issue. Ask them why they aren't doing it? Don't they see the advantages? Is it too much work? (This is Peter the Scrum Master speaking now)

Maybe you could organize a meeting each sprint with as your only goal : give all stories a story point estimation, you can use planning poker do this more easily.

Best regards,

Peter

0 votes
Anthony Steer April 24, 2019

This may be an old question but I have a new solution that works for my scrum team.

 

In the board configuration, set the card colours depending on your chosen criteria.

For my team, I have a criteria that meets the Definition of Ready with a check that the story is not already in the active sprint.  I set the card colour to green for this.  In the backlog, all the stories that meet the DoR but are not in the current sprint are shown with a green card tab.

I also have other card colours that show what is wrong with a story; For example:  Red for no acceptance criteria.  These show the colour even when the story is in the current sprint.  Helps when looking at the sprint board to realise that something important is missing and needs to be addresses sooner rather than later,

0 votes
Mark Scandariato November 22, 2013

I've decided to create a report that will locate stories that are in sprints that do not have an estimate. With this info I can go to Scrum Masters and provide additional training.

Kim Poulsen
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 24, 2013

I think you have made the right decision. Please accept an answer to close the question.

0 votes
Steve Thornhill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 7, 2013

How about setting the estimate field to be required?

Kim Poulsen
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 7, 2013

That would involve a workflow change to add another status that can be transitioned to because Open -> In Progress is already in a sprint.

If the estimate is set to be required on story entry it would completely hamper entry of anything to the project, or get the project estimate count skewed completely due to lots of bogus or zero estimates being entered.

So it can be done but will have consequences.

As I understand the question the problem at hand is that sprints are created and commited to with unestimated issues. This is definitely a team issue.

Suresh Kumar September 18, 2014

how can I set estimate field as mandatory?

0 votes
Mark Scandariato November 6, 2013

I get where you're going with that... but i don't think it will work.

The idea of Sprinting means your sprint team members have commited to completing work/stories by the end of the sprint. The story points measure the teams estimate of that body of work. If there's no estimate, there can be no commitment.... so i don't want stories to be dragged into the sprint without that estimate process happening. I have several teams using JIRA/Greenhopper, so it hard to enforce right now. Any idea's ... (other than additional training!!) I'd just like to enforce it via the tool if possible.

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 6, 2013

You can't block it but in the boards you can update the filter not to show the stories which doesn't have story points. Will that work?