Our "fix version/s" is comprised of issues from our backlog (contained in Project 1) and issues arising out of our production environment (contained in Project 2).
We just upgraded to JIRA Software 7, and are excited about using Boards for ranking and sprint planning.
However, when I expand the VERSIONS tab on the left side of a Scrum board, I see that the issues belonging to the same version, are divided across 2 projects.
It is not desirable to plan sprints for each project, when in effect, the issues belong to the same version.
There's no easy way to manage multi-project version planning within the Software Rapidboards, no.
I'm interested to hear why you have separate projects releasing the same versions, it's an interesting use-case but it's not new...
The use case is: We have 2 concurrent projects - a development project, and a support project. Every release builds a backlog of issues from both projects.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.