Can I use the Release Burndown chart retroactively?

Can I use the Release Burndown chart retroactively? For example I have four prior sprints and a current sprint. Can I add stories/tasks, from my four prior sprints, to a release and then generate a Release Burndown chart?

When I tried this in JIRA I see the my active sprint in the Release Burndown report but my four prior sprints are absent. The JIRA Labs parallel sprints feature was enabled when I defined my release and was subsequently is disabled in an effort to get my prior sprints into my Release Burndown report.

1 answer

In my experience, the Release Burndown chart will only calculate the Stories included in an Active Sprint that is configured on that current board.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 16, 2018 in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

1,383 views 17 10
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you