Can I use the Release Burndown chart retroactively?

Can I use the Release Burndown chart retroactively? For example I have four prior sprints and a current sprint. Can I add stories/tasks, from my four prior sprints, to a release and then generate a Release Burndown chart?

When I tried this in JIRA I see the my active sprint in the Release Burndown report but my four prior sprints are absent. The JIRA Labs parallel sprints feature was enabled when I defined my release and was subsequently is disabled in an effort to get my prior sprints into my Release Burndown report.

1 answer

In my experience, the Release Burndown chart will only calculate the Stories included in an Active Sprint that is configured on that current board.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

94 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you