Can I set "Maximum assignees per story" on an individual epic/story, rather than for the whole plan?

Rob Carpenter September 26, 2017

I have a question about the JIRA Portfolio scheduler configuration.

I would like to be able to set the "Maximum assignees per story" value on individual epics or stories.  It currently looks like this can only be set for the entire plan.

When I'm doing coarse-level planning, I typically want a large work item split between several people.  As I get to finer-level planning, I've broken the work down further, and hence want fewer people to execute a given task.  With just one setting, it doesn't appear that I can meet both objectives at the same time.

Is there a way to configure this per epic/story in portfolio?

Thanks,

Rob

1 answer

1 accepted

1 vote
Answer accepted
Rob Carpenter September 27, 2017

Looks like this is an open feature request: https://jira.atlassian.com/browse/JPOSERVER-1502