Can I re- arrange sprints in plan mode? like I want to see the sprints on scrum board in the order of October, November, impeded, backlog sprint instead of current order October, impeded, November, backlog sprint.
Sarika,
What version of Agile are you using? Similar functionality was released in JIRA Agile 6.6.11: https://confluence.atlassian.com/display/AGILE/JIRA+Agile+6.6.11+Release+Notes
Simply update your JIRA Agile and you should be set
Thanks for the response .
Version 6.6.13 looks so cool but we are in V6.1 which has long way to go to reach 6.6.13 version.
I can't update JIRA Agile on my own, it has to go through JIRA admins in the organization, will check with them in this regards.
Is there a way to do this in JIRA Agile V6.1 by any chance?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ah, unfortunately not unless you manually move each issue between sprints. That would be the only way around it, which also could cause a lot of human error. With any luck your admins can help update this for you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.