Can I leave the Story task in the backlog and add the story's subtasks to the current sprint board? Not just tag with the correct fix version but to actually see it on the active sprint board?
Thank you!
No, there's no way to do this.
Sub-tasks are not independent items, they aren't even items you can commit to in a sprint. They only become part of a sprint by virtue of being a part of an issue that does go into it.
If you want to handle them separately to thing of which they are a part, you can convert them to issues (stories) in their own right, then they will be sprint-enabled items.
Thank you so much for the quick reply.
To ensure, all the Epic tasks can be managed separately? Can I put them in different sprints and leave the Epic itself out of the sprints?
Thanks again!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Epics are a separate thing again - they are a layer above issues (stories). They are not expected to go into sprints, they're expected to act as a grouping of many issues (that do go through sprints), ending when all their component stories are finished.
So, yes, you can (and should) handle Epics separately, and outside sprints.