Hi All,
During planning, I want to estimate story in story points and sub-task in original time estimates. Can I acheive this result in JIRA ? If yes then please guide me.
Thanks in advance.
Yes, you can. You will probably just need to add the "time tracking" field to the screens used to create and edit the sub-tasks (the default config does not do it)
Bear in mind that if you're doing Scrum, you will only be able to work with one of these two for velocity etc, and for your set up, that one should be Story Points.