Can I estimate story on story points and sub task on original time estimates at the same time ?

Hi All,

 

During planning, I want to estimate story in story points  and sub-task in original time estimates. Can I acheive this result in JIRA ? If yes then please guide me.

 

Thanks in advance.

1 answer

0 votes

Yes, you can.  You will probably just need to add the "time tracking" field to the screens used to create and edit the sub-tasks (the default config does not do it)

Bear in mind that if you're doing Scrum, you will only be able to work with one of these two for velocity etc, and for your set up, that one should be Story Points.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,886 views 12 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot