Can I customize the version report with average velocity?

For new teams, I would like to enter manually an estimated average velocity.

Is that possible?

1 answer

1 accepted

0 votes
Accepted answer

Hi Orit,

Per the Viewing the Velocity Chart knowledge base article, the Velocity chart always shows your last seven completed sprints.  This is where that data is coming from in the Version report and I have not found a way to modify this.

In light of this please go to JAC and create a Suggestion and post the link here so the Community can vote on this issue and add impact so we can get this implemented into a future iteration of JIRA.

Cheers,

Branden

Thanks! 

Here is the link to my suggestion: JRASERVER-66711

Thanks for posting the link!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,777 views 18 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you