Can I configure sub tasks to block their parents automatically?

Shmulik Kaplan February 16, 2015

I want be able to configure JIRA so that each time I open a new sub tasks it automatically links to its parent and blocks it. 

Can it be done?

1 answer

1 accepted

0 votes
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 16, 2015

What do you mean by block it? It is possible to configure workflow to block parent transitions when there are open subtasks. Is that waht you are looking for?

Shmulik Kaplan February 16, 2015

If by "parent transitions" you mean that I can not close the parent task  before I close all its sub-tasks then this is exactly what I want.

Where can I find how can I do that?


Thanks 

Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 16, 2015
Shmulik Kaplan February 16, 2015

Thank you very much