Can I change how sum of time spent is displayed on issue cards on the board?

Teal Nissley August 19, 2015

I would like the sum of time spent to display in hours, not days-hours-minutes. Is this possible to customize?

2 answers

1 accepted

0 votes
Answer accepted
Pilar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 19, 2015

Yes you can.

You need to go into administration ->System ->Time tracking.

Deactivate time tracking and then select time format to hours. Then re-enable time tracking.

here is the link for more details

https://confluence.atlassian.com/display/JIRA/Configuring+Time+Tracking

Pilar

0 votes
Teal Nissley August 19, 2015

Perfect, thank you!