Can I add story points to Stories in an active sprint?

During the sprint planning, we missed adding story points to a couple of stories planned for the sprint. When we started the sprint, those particular stories have zero story points.

Now, we're trying to add the story points, even though the sprint is already halfway finished. But, I don't seem to see way to actually add them.

Is this possible, and if so, where would I need to edit the issue to add them?

Thanks in advance for any advice.

1 answer

1 accepted

This widget could not be displayed.

Actually, I figured out a bit of a brute force solution. Just move the story out of the sprint, edit the story points, and move it back in. JIRA will throw some warnings, but at least it seems to work. No idea if this screws up burndown charts or anything, but it seems to be ok.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

139 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you