By Using Time tracking am able to get efforts appropriately is there a way to figure out % Complete

Raj Navale December 21, 2021

Need help on how the % Complete value is taken for a story

Note that i have created sub tasks and given Original estimate and updating time spent on a daily basis. 

Pls let me know how can i get the % complete value

1 answer

0 votes
John Driscoll January 3, 2022

I'd try creating a custom field (% complete) and building an automation to update the value each time the Hours Worked field in the jira story is updated.

  1. When: Value changes for "Hours Worked"
  2. Then:  Edit issue fields "% Complete"

        build a JSON script within the 2nd step of the automation to do the math
          (hours worked/ estimated hours)

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events