Hi, I need help on an issue please.
It's our first Sprint with Jira. Today, we moved a Task of 8 story points to Done, but the Burndown is not showing this change. Anyone with the same issue or know how to solve it?
Thanks!!
Is your "done" status in the last column on the board?
It's not, but the unique column in the board that has "Set resolution" as active is the Done column. Has Done column to be on the last column of the board?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Fantasy, please be sure that you are setting the Resolution field for any issue that moves to Done. Jira requires that filed for burn down.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.