Burndown chart show as a red horizontal line

Hi i am using scrum board in jira , i have customized column set . To Do Development In Progress Ready For Code Review Code Review In Progress Ready For Testing Testing In Progress Approved For Release Released Approved ,

instead of new , in progress , to do .

in my burn-down chart even after i added spent time or make the task approved , the burn down chart is shown as a strait red horizontal line , why is that ?

1 answer

The Burndow works obviously with issues added and estimation added before the sprint has started. Log work after the sprint has started and before it is completed.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,076 views 13 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot