Burndown chart is not displaying the estimations .

mallikarjun kalal August 10, 2015

We have started a sprint without  estimations after start of the sprint we changed the estimations . So burndown chart is not displaying the estimations .

Is there any troubleshooting steps to get proper reports for all estimations?

If we close the  existing sprint  and if We start another sprint with same Start Date: and End Date of sprint as existing sprint . also moving all issues to new sprint from  existing sprint. Will those Original Estimates reflect in the new sprint ?

 or 

 Is there any other better solution to get proper report for below issue ?

1 answer

0 votes
GabrielleJ
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 11, 2015

I suggest closing that Sprint and just start a fresh new one. The old one will be unusable anyway.

mallikarjun kalal August 12, 2015

Thank you. we will close that sprint and If we start a new sprint with start date (10-july-2015) and end date (10-Aug-2015) and moving all those closed sprint issues to new sprint. can we get proper report ? thanks