Burndown chart is not displaying the estimations .

We have started a sprint without  estimations after start of the sprint we changed the estimations . So burndown chart is not displaying the estimations .

Is there any troubleshooting steps to get proper reports for all estimations?

If we close the  existing sprint  and if We start another sprint with same Start Date: and End Date of sprint as existing sprint . also moving all issues to new sprint from  existing sprint. Will those Original Estimates reflect in the new sprint ?

 or 

 Is there any other better solution to get proper report for below issue ?

1 answer

I suggest closing that Sprint and just start a fresh new one. The old one will be unusable anyway.

Thank you. we will close that sprint and If we start a new sprint with start date (10-july-2015) and end date (10-Aug-2015) and moving all those closed sprint issues to new sprint. can we get proper report ? thanks

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

243 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you