Burndown Chart > Original Time Estimate - scope change tracking behaviour during sprint

I have Time Tracking enabled.

Before sprint start, I have estimated all sub-tasks and only sub-tasks original and remaining estimates. 

Upon sprint start, the burndown chart shows a starting Original Time Estimate of 168h. (I am able to switch chart between Original Time Estimate, Remaining Time Estimate and Story Points)

Halfway during the sprint, a team member added 2 sub-tasks to an existing Story, and then edited the Original and Remaining estimate of the sub-task (like before the sprint start).

I expect the Original Time Estimate to increase due to the scope change, but there is no change in the timings on the chart.

May I know what is the intended behavior for scope changes during mid-sprint? If:

  1. issues are added/removed,
  2. sub-tasks are added/removed,
  3. issues or sub-tasks are moved to become sub-tasks or issues respectively within the same sprint?

1 answer

0 vote
Warren Levy Community Champion Aug 07, 2017

Hi Jake

You certainly should see a change to both Original and Remaining estimate, as per below :

Picture0006.jpg

Remember that if your baseline is 168h and you only add say 1h, it may not really show because of the scale.

Look lower down on the burndown page in Jira and you should see an entry like

Picture0007.jpgfor each item brought in or removed. The third column shown there is the time change for removed items and the 6th column is the time change for added items.

Remember that the time on all subtasks totals to the time on the parent issue, so your 1 and 2 above are essentially the same question, as is 3

Hi Warren,

The issue is that in my Remaining Time Estimate chart, I have 3 Scope change (Issue added to sprint) with 5h, 5,h and 3h increase, but the same is not reflected in the Original Time Estimate. I am pretty sure that your screenshot is showing data for Remaining Time Estimate, not Original Time Estimate.

I checked the 3 tasks, all three of them have Original Time Estimates entered. On the Original Ttime Estimates chart (and data table), the 3 entries cannot be found.

May I know what am I missing? Thanks.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Thursday in Jira

5 ways you can make the most of Jira Software and Bitbucket Cloud

As part of the Bitbucket product team I'm always interested in better understanding what kind of impact the use of our tools have on the way you work. In a recent study we conducted of software devel...

110 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you