Hi All
It seems this is a bug with tempo log work screen.
If i log some time through the tempo log work screen, then the tempo interface and the jira issue shows the logged effort. However, the sprint burndown chart does not recognise the effort i logged in through the tempo interface.
Please note this is not the case if i use the jira log work screen to log work.
Is there any fix or workaround to this issue?
rahul
I got this response from Tempo support team
" I was checking with the dev team, and I think we found the problem.
When you log time through Tempo without start time, the worklogs automatically get the timestamp "midnight". The burndown in JIRA Agile shows the time logged until "now", so hours logged in Tempo will not show up until after midnight.
To avoid this, you can check the "Log work with start time" in the Tempo Global Configuration (Administration-> Add-ons, Tempo Global Configuration, in the Time Tracking Permissions and Validation section). When using this, all worklogs should show up in the burndown as soon as you log them."