BigPicture - Removing dotted red lines on Gantt Chart

red-lines.PNG

 

I'm trying to remove this dotted red line on this gantt chart. Is there any way to remove this without an additional plugin?

1 answer

Hi Logan,

The red-dotted line (orange-dotted in newer versions) indicates the position of the parent task after it is recalculated based on its children. This happens when manual mode is enabled or the issue is locked.

You can read more about task modes here.

Cheers,

Patryk

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you