Hi, I do NOT want to autoschedule issues in BigGantt. Is there a way to switch this feature off ? Globally or even for each Gantt?
Currently I can indicate manual scheduling within in a particular Gantt, it then adds a manual scheduling icon to each issue in the Gantt. But when a new issue is created in JIRA and I re-sync the Gantt, that new issue does not have the manual scheduling flag . So I have to see and correct BEFORE doing any scheduling changes. This is FAR to dangerous for us.
Hi,
Please switch off the auto scheduling in DATA -> SCHEDULING -> manual.
Also make sure the Gantt config synchronization and "recalculate parents" is off.