BigGantt autoschedule : switch off globally or for a specific Gantt

Hi, I do NOT want to autoschedule issues in BigGantt. Is there a way to switch this feature off ? Globally or even for each Gantt?

Currently I can indicate manual scheduling within in a particular Gantt, it then adds a manual scheduling icon to each issue in the Gantt. But when a new issue is created in JIRA and I re-sync the Gantt, that new issue does not have the manual scheduling flag sad. So I have to see  and correct BEFORE doing any scheduling changes. This is FAR to dangerous for us.

1 answer

Hi,

Please switch off the auto scheduling in DATA -> SCHEDULING -> manual.

Also make sure the Gantt config synchronization and "recalculate parents" is off.

 

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

24,164 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you