BigGantt Start & End Dates keep resetting

Yewliang Woo
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 6, 2024

In the BigGantt plugin, when I change the Start and End date in the in the Jira issue, it gets changed, and automatically resets back to the old value after a second.

THis is not a question - but a note for others struglling with this.

If this happens, it may be because the Scheduling Mode may be 'locked'. Change it to any other mode by right-clicking on the Gantt.

1 answer

0 votes
Mirek
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 30, 2024

Thank you @Yewliang Woo for sharing the tip! It would be definitively helpful for people that might struggle with ehe same issue. 