Before the actions which are Sub-Task been completed, the Task which SUB-TASK is related not be closed. How can I do this?

Alper AYKUT October 7, 2015

Before the actions which are Sub-Task been completed, the Task which SUB-TASK is related not be closed.  How can I do this?

1 answer

2 votes
Jeremy Gaudet
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 7, 2015

If I understand the question correctly, you want to add a condition to the "Close" transition in the workflow, of type "Sub-Task Blocking Condition", then select "Closed" as the only sub-task status.