Automatically update original estimate of parent ticket based on sum of sub-task estimates

I am using Original time estimate as estimation statistic instead of story points to calculate velocity. During planning, we put time estimates in subtask level. How can the parent ticket be automatically updated with the sum of subtask estimates?

 

Thanks

1 answer

normally the parent task has all the subtasks values as a sum

subtask:

original estimate

paren task:

Σ original estimate

 

in JQL view, just ust the fileds with the Σ (they are also working for the subtasks)

Thanks for responding, I somehow got it figured out yesterday using the automation rules. I used a "start of sprint trigger" for this rule to be executed and original estimate to be populated based on the sub-task estimates:
original-estimate-automation-rule.PNG

ramya I'm New Here May 31, 2021

@Angela Salunga 

Rule pasted in your previous comment, is it complete or any prefix is missing?

Because construction of rule doesn't start with condition.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Site Admin
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you