If I have workflow: Waiting To Do >To Do >In Progress> Done.
Can tasks automatically change the status of "Waiting To Do" to "To Do" when I click Start Sprint?
Is this option somewhere in the settings?

1 answer

1 accepted

This widget could not be displayed.
Steven Behnke Community Champion Dec 07, 2016

This isn't possible out-of-the-box. You should be able to Shift+Click all of the items in a sprint, right click, and bulk transition them all at once though.

You can probably accomplish this with one of the nifty new automation plugins too.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

262 views 1 3
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you