Hi,
could you please any one help me out in assigning the dead line dates to the sub tasks based on the parent issue type.
for example, if the BUG issue type due date is 12/31/2015. if there are 4 sub tasks for that issue type then i want the due dates to be assigned to the sub tasks like, for example,
sub task one 12/24/2015
sub task two 12/26/2015
sub task three 12/28/2015
sub task four 12/30/2015.
Thank you
surender
I understand Adaptavist users suggesting their own product. Scriptrunner is a great plugin, totally worth the money. I'd recommend it for pretty much any setup.
In this particular case, even if you already have scriptrunner, there's an easier alternative: you could use the Quick Subtasks plugin. For free.
It does exactly what you require with the subtasks by having them inherit the due date of the parent issue, +- a certain amount of days.
You can maintain templates for all issue types that tend to have the same subtasks.
https://bitbucket.org/hascode/jira-quick-subtasks/wiki/Home#markdown-header-due-date
Hi surender,
One way to do this is using script runner for JIRA plugin. If you are familiar with groovy language then you can write a very simple script that will do this for you ad hoc by just executing the script using the script console or every time a transition in the workflow is happening or though a listener that will execute the script when an event takes place, you can have a look at the documentation. If you decide to try this approach then you can get further assistance here.
Kind regards
Thanos