Hey all,

I am looking for a way to close all sub-tasks when the parent closes. I came across the Post Function here but I'm afraid it's not working for me.

We are on JIRA 5.0.2 with Script Runner 2.0.7

Any ideas?

4 answers

"not working for me", it doesn't help us to help you!!

what is the error message you are getting on log file ?

This is the error: javax.script.ScriptException: groovy.lang.MissingPropertyException: No such property: transientVars for class: Script4

Found a ticket on GRV [GRV-125] and tried Jamie's comment: I have no idea. Just for a test replace the line

String currentUser = ((WorkflowContext) transientVars.get("context")).getCaller();

with

String currentUser = ComponentManager.getInstance().getUserUtil().getUser("admin").getName()

In that string change admin to a user that has permission to do the transition.

Then I get this error: javax.script.ScriptException: groovy.lang.MissingPropertyException: No such property: issue for class: Script23

0 vote
Henning Tietgens Community Champion Jan 08, 2014

Try to place the script at the end of the postfunctions list and tell us if this change anything.

It doesn't change anything

Hello,

I'm using the same code from the example above (here) for default workflow (just testing ;) ) and instead of closed sub-tasks I've got sth like this:

groovy.lang.MissingPropertyException: No such property: a for class: Script2

I must admit that I am not best in 'grooving'- could anyone help me? I would really appreciate.

We are on JIRA 6.0.4 with Script Runner 2.1.17
Best wishes,
JW

There's now a very easy to configure way to transition parents and sub-tasks in sync using Automation for JIRA!

You can easily modify related issues (such as parents, stories, sub-tasks, epics, linked issues and even JQL) using our related issues action and condition:

(this example transitions sub-tasks to "In Progress", but you could easily change this to "Closed" as well)

For more details see https://blog.codebarrel.io/synchronize-parent-and-sub-task-issues-with-automation-for-jira-bdcca6c9d453

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,316 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot