Artezio Burndown Chart "Can't draw burndown chart! No remaining estimate at the starting date"

I am evaluating the Artezio Burndown Chart. I have a test issue I created and a filter that grabs that issue. The issue has an initial estimate of 4d, a remaining estimate of 3d 5h 30m, and logged hours of 2h 30m. The Start Date is Jul 1st 2014.

But, when I try to create a burndown chart that starts on July 1st I keep getting this error: "Can't draw burndown chart! No remaining estimate at the starting date" even tho I can clearly see in the issue itself a remaining estimate of 3d 5h 30m. Anyone know of a way to get this to work? I look on Artezio's website for a user forum or FAQs, found nothing.

1 answer

My apologies for the delay with the answer. These are the specifics of the plugin. The chart is based on two points - remaining estimate for a start day and the end of a day. If the issue was created on June 1, for the beginning of the day it didn't exist yet. If you choose as starting date June 2 the chart will be displayed.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,252 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot