I'm not a hundred per cent sure if this is a limitation in JIRA or in Zephyr but I've seen other user posting about the same use case:
https://answers.atlassian.com/questions/15297677
The problem is we can't copy test cycles between projects. The reason to do that is because we've changed from Waterfall into Agile and want to have our cycles distributed across different teams/projects while also REusing the test cycles we already had.
How come this is not possible?
Below is an step by step example I created to prove this.:
Screen Shot 2015-05-15 at 2.05.10 PM.png
Screen Shot 2015-05-15 at 2.18.22 PM.png
obviously if there's a drop down allowing you to select the destination project it means you SHOULD be able to do just that, but instead you get this:
Screen Shot 2015-05-15 at 2.20.06 PM.png
Is there any update on this, I could use this feature right now.
Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.