Agile Board Backlog + Allocated Sprint Items Not Equal To Filter Total

My current sprint using the agile scrum board has 49 tickets/stories.  My backlog has 149 tickets/stories.  My filter has 247 tickets/stories.  All of the missing items fail to show on the backlog total.  Any ideas?

1 answer

1 vote

Do you have 98 sub-tasks in the filter?

That is where I was headed.  sub tasks bring me within 8. 

Ok, I'm not sure what "within 8" means?  8 over/under what?

Of the 8 that are mismatched though, is there a pattern to them?  Same issue type for example?

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,300 views 12 19
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you