Agiel Burndown widget and Guideline at zero

Hello,

I set up my projet in agile mode with sprints. I wanted to use the burndownchart on my dashboard. Unfortunately the Guideline is alway at zero(see screenshot bellow). I found people speaking about launching the sprint after having associate task, or moving the dates to solve this problem, but any of this solutions solve this.  Does any one have any solution ? 

screen.png

1 answer

Check your tracking statistic , it should be set to original time estimate.

Secondly, make sure you estimate and add stories in your sprint and THEN start the sprint. If you start the sprint before adding stories in it then guideline will show you zero.

Pilar

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

25,286 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you