Adjust capacity to account for holidays in Jira Agile

We have recently migrated from Pivotal Tracker, and I am wondering how I can fine time the capacity of the team/individuals to ensure more accurate projections.

2 answers

In jira-agile you can make use of the velocity charts which tracks how much your teams delivered on the sprint commitments. Say, you have 5 developers and in two weeks , you achieved 30 story points out of 50. Then you know your teams velocity is 60% and you can apply this number to future sprints.

You will however need to go through a few sprints to get to a point where you can use the data to make more accurate predictions.

Hope this helps.

Pilar

Thanks for your reply Pilar,

Not sure I understand what you mean by:

and you can apply this number to future sprints

after it has been "applied", will all projections be recalculated?

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

25,463 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you