Adding a a defect to an active sprint change the scope? How to avoid changing the scope

Srinivasa HP May 4, 2016
 

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 4, 2016

You don't.  If you are adding things to a sprint, you're changing the scope.  JIRA Software recognises and reports on that.

Srinivasa HP May 4, 2016

It means you are not supposed to add a defect to a current sprint which is active???

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 4, 2016

Correct.  The very definition of "scope change" is "you add things you did not originally plan for into the sprint".

You either accept that you are changing the sprint or leave it for the next sprint!