Adding Work into Existing Release in Portfolio

We had a need to add some important work into an existing release that is in progress of being executed.  When this work was added, Portfolio timeline shows the work at the beginning of the release which is a few weeks in the past.  So it did not apply the current date into the calculation of where it needs to fit in the timeline.

 

What needs to be set for it to take the current date into consideration and correct the timeline?

We use Kanban

1 answer

JIRA Portfolio is focused on planning and report on overall progress. I want to re-iterate that this is a planning tool.

The only consideration for current date is when it's calculating the expected progress of a release vs. what work has been done. These are all overall progress calculations and not individual ticket calculations. When new work is added, it is still a planning out the whole picture of the release, it does not calculate how new work fits into the current date.

If you'd like a better picture of scope changes, then using Agile Scrum Boards are likely better suited for this case.

Regards,

David Chan

Atlassian Premier Support

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

959 views 3 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you