Adding Work into Existing Release in Portfolio

We had a need to add some important work into an existing release that is in progress of being executed.  When this work was added, Portfolio timeline shows the work at the beginning of the release which is a few weeks in the past.  So it did not apply the current date into the calculation of where it needs to fit in the timeline.

 

What needs to be set for it to take the current date into consideration and correct the timeline?

We use Kanban

1 answer

JIRA Portfolio is focused on planning and report on overall progress. I want to re-iterate that this is a planning tool.

The only consideration for current date is when it's calculating the expected progress of a release vs. what work has been done. These are all overall progress calculations and not individual ticket calculations. When new work is added, it is still a planning out the whole picture of the release, it does not calculate how new work fits into the current date.

If you'd like a better picture of scope changes, then using Agile Scrum Boards are likely better suited for this case.

Regards,

David Chan

Atlassian Premier Support

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

21,157 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you