Add new Project to existing Portfolio Plan

I've created a new project, which it has their own team and board, and I would like to add it to an existing portfolio plan and be able to create a new cross-project release and link it to this new project. 
When I am creating the cross-project release and I do not see the project on the list. how do I link it?
When I am looking the list of the teams under the plan, the new team its not linked to the project's board. how do I link it?

Thanks

1 answer

This widget could not be displayed.

Hi Jaime, 

 

You will need to edit the Issue Source for the plan in order to include the new project. You can get more information in:

Edit Issue Source for a Portfolio Plan

 

After this, you can create a cross-project release including the new project. You might find the following documentation helpful:

Creating and configuring cross-project releases

 

To link a Team to a source, click on the button under the Team name and associate it with a source:

assosiate source to team.png

Let me know how it goes. 

 

Maja

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

182 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you