Add new Project to existing Portfolio Plan

I've created a new project, which it has their own team and board, and I would like to add it to an existing portfolio plan and be able to create a new cross-project release and link it to this new project. 
When I am creating the cross-project release and I do not see the project on the list. how do I link it?
When I am looking the list of the teams under the plan, the new team its not linked to the project's board. how do I link it?

Thanks

1 answer

1 votes

Hi Jaime, 

 

You will need to edit the Issue Source for the plan in order to include the new project. You can get more information in:

Edit Issue Source for a Portfolio Plan

 

After this, you can create a cross-project release including the new project. You might find the following documentation helpful:

Creating and configuring cross-project releases

 

To link a Team to a source, click on the button under the Team name and associate it with a source:

assosiate source to team.png

Let me know how it goes. 

 

Maja

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,087 views 13 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot