Active Sprint with Items Crossed

Hello, 

I have created a new project with new sprint. I imported issues via CSV and later on i changed the sprint date and edited its name because it was showing Sprint 3. I changed it to Sprint 2. Furthermore before doing all of it i closed one sprint of my last project.

Now i see Sprint 1, Sprint 1 in Sprint field and when i see issue detail. it says Completed Sprint 1. This is quite confusing for me if any one help me on this would be grateful  alot.

 

Items in new project Sprint 1 are crossed as if they are done. 

1 answer

Hi Aamer,

The items crossed you mentioned from sprint 1 are possibly showing up like this because even though they are not done, they have a resolution set. The issues only receive a strikethrough in the board when they have a resolution set.

Could you verify if this is occurring with issues without resolution as well?

Cheers

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,307 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot