A Sprint from one project/board appears also as the active sprint in another project

Oren Tayar November 27, 2019

Hi,

I'm the PO in two projects/teams.

I have seperate stories in each project/backlog. 

We run this way for a while where each project/board has its own sprints and active sprint in parallel.

Something happened where suddenly Active sprint of project A appears as active (with no stories) also in project/board B.

The problem now is that I can't start a new sprint in B untill the sprint of A will finish ... 

1 answer

0 votes
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 27, 2019

Hi @Oren Tayar 

So if this has been working successfully for a while, do you know what has changed that it suddenly isn't working? If so, you need to try and revert that change.

My suggestion would be to look at the board Filter query for each project, check if project A's filter references project B or vice versa. The filter can be found by going to the Board settings and checking in the General tab